Q1: What is the main production process of thick-walled seamless pipes?
The production of thick-walled seamless pipes includes the following key steps: round billet heating (1200±50℃) → piercing (pressure piercing or oblique rolling piercing) → elongation rolling (such as Assel rolling mill) → sizing → heat treatment (normalizing or quenching and tempering) → straightening → non-destructive testing → water pressure test. Among them, the piercing link is particularly critical for thick-walled pipes, requiring large-diameter billets (such as Φ350mm) and multiple rolling passes. Modern continuous rolling mills (such as MPM) can produce seamless pipes with a diameter of Φ60-460mm and a wall thickness of up to 120mm, and the production efficiency is 3 times higher than that of traditional methods.
Q2: What are the manufacturing process characteristics of thick-walled straight seam submerged arc welded pipes (SAWL)?
SAWL thick-walled pipe production process: ultrasonic flaw detection of steel plate → milling edge (groove 30℃±2℃) → JCO or UOE forming → pre-welding (TIG primer) → multi-wire submerged arc welding (4-5 wires, current 800-1200A) → diameter expansion (1.0-1.2%) → heat treatment (stress relief annealing). The key technology is to control the welding heat input (20-35kJ/cm) to avoid HAZ embrittlement, and use X-ray + ultrasonic double flaw detection to ensure weld quality. This process is suitable for pipes with a diameter of Φ406-1626mm and a wall thickness of 20-60mm, with a production efficiency of about 1-2 meters/minute.
Q3: What are the key control parameters for heat treatment of thick-walled steel pipes?
Heat treatment of thick-walled pipes needs to be strictly controlled: normalizing temperature (Ac3+30-50℃, such as 890±10℃ for 20# steel), holding time (1 hour for every 25mm of wall thickness), cooling rate (air cooling ≤3℃/s); water cooling rate during quenching needs to be >30℃/s to avoid ferrite precipitation; tempering temperature (such as 680±10℃ for 15CrMoV steel) and time (wall thickness × 2.4 minutes/mm). For extra-thick walls (>100mm), differential temperature heat treatment technology is required to ensure core performance. The hardness gradient after heat treatment should be controlled within the range of ±20HBW.
Q4: What is the residual stress control method in the production of thick-walled steel pipes?
Excessive residual stress can lead to deformation or stress corrosion. Control measures include: hot straightening after rolling (600±50℃), overall annealing (580-650℃ insulation for 4-8 hours), vibration aging (VSR) treatment, mechanical expansion (1.0-1.5% deformation) and explosive stress relief. For welded thick-walled pipes, multi-layer multi-pass welding + interlayer hammering process is required. Residual stress detection can be carried out by X-ray diffraction method or blind hole method, requiring surface residual compressive stress >=-200MPa.
Q5: What are the special requirements for quality inspection of thick-walled steel pipes?
In addition to conventional inspections, thick-walled pipes need to add: Z-axis tensile test (section reduction rate >=35%), step cooling test (assessment of temper brittleness), UT flaw detection (dual crystal probe detection of internal defects), TOFD detection (quantification of weld defects) and hardness scanning (full-section Brinell hardness test). For nuclear power pipes, grain size rating (grade 5-8) and purity analysis ([O]<=20ppm) are also required. Wall thickness measurement requires a high-frequency ultrasonic thickness gauge with an accuracy of ±0.1mm.